Local Plan timetable

The timetable for the 30-month process of preparing the new Local Plan

Hart District Council is preparing a new Local Plan under the revised plan-making system introduced through the Levelling Up and Regeneration Act 2023 and the Town and Country Planning (Local Planning) (England) Regulations 2026. 

This document sets out the timetable for preparation of the new Hart Local Plan (the ‘Plan’), in line with the government’s new 30-month local plan process and associated guidance. As well as being published on the Hart District Council website, this timetable will also be available to view at key Council locations and copies can be made available to members of the public on request.

Once adopted, the new Hart Local Plan will replace: 

What will the new Local Plan cover?

The new Hart Local Plan will apply to the geographical area of Hart District (see Figure 1 below). 

It will provide a long-term planning framework, including a vision and strategic priorities for the District, setting out the overall amount and distribution of new development, site allocations and other policies for the determination of planning applications. A Policies Map will accompany the Plan and illustrate geographically where its policies apply.

Timetable dates

This Local Plan Timetable takes effect from 26 October 2026.  

Publish notice of intention to commence plan preparation 

29 April 2026

Hart District Council published a Notice of intention to commence plan preparation.  

Scoping consultation

27 May 2026 – 19 June 2026

An early consultation took place to seek views from stakeholders on the scope of the Plan and how they wish to be engaged during the plan-making process. This was a public consultation; any individual or organisation could submit comments.

A summary of the consultation and responses received will be published before we start the consultation on the proposed plan content and evidence.

Gateway 1 

23 September 2026

Hart District Council published the Gateway 1 Self-Assessment Summary demonstrating readiness to prepare a sound Local Plan. This milestone formally marks the start of the 30-month plan preparation period.

Consultation on proposed plan content and evidence 

26 October 2026 – 7 December 2026

A consultation on the proposed plan content and evidence was published on 26 October 2026.  Views are sought on the Plan's draft vision, proposed spatial strategy and a summary of evidence gathered to date. This is the first formal consultation during the 30-month plan preparation period. The consultation will last for six weeks, after which a summary of the consultation and of responses received will be published.

Gateway 2

30 June 2027 – 30 July 2027

Hart District Council will meet with the Planning Inspectorate, where an appointed gateway assessor will review progress on the Plan. The purpose of Gateway 2 is to identify and resolve potential soundness issues early and to ensure that the Plan is on track to meet legal requirements. Once the Gateway 2 assessment is complete, the assessor’s formal report and observations will be published.

Consultation on the proposed plan 

3 September 2027 – 29 October 2027

This is the second and final formal consultation during the 30-month plan preparation period and is a consultation on the full draft plan and policies map. The consultation will last for eight weeks, after which a summary of the consultation and of responses received will be published. 

Gateway 3 

3 January 2028 – 29 February 2028

Gateway 3 is the final assessment stage by the Planning Inspectorate before the Plan can be submitted for examination. The gateway assessor will decide whether the Plan is ready for submission, based on prescribed requirements on legal compliance and the completeness of the submission documents. Following the assessment, the assessor’s report, submitted documents and a Gateway 3 completion statement will be published.

Plan submission

31 March 2028

Subject to passing Gateway 3, the Plan and all supporting evidence will be formally submitted to the Secretary of State for independent examination. 

Plan examination

31 March 2028 – 31 August 2028

An Independent Inspector, appointed by the Secretary of State, will examine the Plan to determine whether it is sound and compliant with national planning policy. 

Plan adoption

31 October 2028

The Plan will be considered for adoption. Once adopted, the Plan will form part of the statutory Development Plan for the District.

The timetable will be kept under review and updated as necessary throughout the plan-making process.

Further information including neighbourhood plans, supplementary planning documents and other planning policy matters is available on our planning policy pages.

Local Plan timetable CSV download

This CSV file contains the information above and will be updated when changes have been made to the timetable and when milestones have been met. The data within this file is being provided to government under the Open Government Licence.

Local Plan Timetable (CSV)

Schedule of amendments

Hart District Council will maintain and publish a schedule of any amendments made to this timetable. 

26 October 2026

The timetable was updated following publication of the consultation on proposed plan content and evidence to include the  associated links.

14 October 2026

The timetable was updated to reflect revised dates for the consultation on proposed plan content and evidence.

23 September 2026

The timetable was updated following completion of Gateway 1 to publish the self-assessment summary and associated links.

Published 29 April 2026

Last updated 26 October 2026

Figure 1 New Hart Local Plan Area Boundary

Image
Map of Hart district


 

 

Is this page helpful?

Is this page helpful?
Don't forget to leave your email if you need further information.
If reporting a broken link, please give the url you were trying to use or the information which you were looking for.
Last reviewed: