Road closure: A3013 Cove Road and Bagwell Lane

South East Water are carrying out a water main installation project between Fleet and Odiham. The £10 million project will see 11 kilometres of pipeline installed to reinforce their network and draw in larger volumes of water from other areas of the underground system.

The project will take approximately 21 months to complete. Over the course of the project the following roads will have construction work: Cove Road, Fleet Road and Elvetham Heath Way in Fleet. Pale Lane, Dunleys Hill, Poland Lane, Bagwell Lane and Odiham Road, Hook. Other impacted roads include Winchfield Road and The Hurst.

Here you can view the current road closure orders and diversion maps.  

South East Water has put together a project timescale – please see the first phase below.

Project timetable

Location

Start Date

Approx Duration

Planned end date

Traffic management plans

Poland Lane

14/6/21

10 days

25/6/21

Road closure

Odiham Road crossing

28/6/21

3 days

30/6/21

4-way lights

Bagwell Lane S

1/7/21

33 weeks

14/2/22

Road closure

 

Cove Road East of Ancells Roundabout

5/7/2021

6.5 weeks

6/9/21

Road Closure

Cove Road Ancells Roundabout

7/9/21

3 weeks

28/9/21

Side road closure/traffic lights

Cove Road West of Ancells Roundabout

29/9/21

4 days

4/10/21

Road closure

Attenborough Close Crossing

5/10/21

3 days

8/10/21

Stop and go boards

Cove Road

11/10/21

20 days

5/11/21

Road closure

Old Cove Road crossing

8/11/21

3 days

11/11/21

Stop and go

Cove Road

11/11/21

Two weeks

26/11/21

Road closure

Total Cove Road section

5/7/21

21 weeks

26/11/21

Mixture of Road Closure and traffic lights/stop-go boards

For more information about the project, please visit the South East Water website.