Temporary Traffic Regulation Orders
A Temporary Traffic Regulation Order (TTRO) can be made by the Council when it is necessary to prohibit or control vehicular and / or pedestrian traffic along a highway because of planned works on or near the road; because of the likelihood of danger to the public or damage to the road or for litter clearing and street cleansing purposes.
TTROs are normally used to allow essential or emergency works to be carried out on the highway. Examples of TTROs include:
- Road closures
- Prohibitions of waiting
- Speed limits
The following table lists current TTROs:
| Location | Type of TTRO | Start Date | Legal Duration | Expected length of closure |
|
Crookham Road, Fleet |
Road Closure | 23/03/10 | 6 mths | 1 day (9am-1pm) |
|
Montgomery Lane, Crondall |
Road Closure | 26/10/09 |
12 mths (original order made 26/10/09) |
1 week |
|
Crondall Road, Crookham Village, & Chalky/Church Lane, Dogmersfield |
Emergency Road Closure | 01/03/10 | 21 days | Intermittent |
|
Devil's Highway, Heckfield |
Road Closure | 05/03/10 |
12 mths (original order made 26/10/09) |
1 week |
|
Thackhams Lane, Hartley Wintney |
Road Closure | 05/03/10 |
12 mths (original order made 07/09/09) |
1 week |
|
Hook Road, Greywell |
Road Closure | 01/03/10 |
12 mths (original order made 26/10/09 |
1 wk |
|
Ewshot Lane, Ewshot |
Road Closure | 23/02/10 |
12 mths (original order made 04/05/09 |
8-10 wks |
|
Hook Road North Warnborough |
Road Closure | 20/02/10 |
12 mths (original order made 27/07/09) |
2 days |
|
Dippenhall Road, Crondall |
Road Closure | 15/02/10 | 6 mths | 4 wks |
|
Hardings Lane. Hartley Wintney |
Road Closure | 15/02/10 | 6 mths | 1 wk |
|
King Street, Odiham |
Road Closure | 21/02/10 | 6 mths | 1 day |
|
Newnham Road, Hook |
Road Closure | 22/02/10 |
12 mths (original order made 26/10/09) |
1 wk |
|
Church Street, Odiham |
Road Closure | 08/02/10 |
6 mths (original order made 17/08/09) |
5 days |
|
Willow Lane, Blackwater |
Road Closure | 28/01/10 | 6 mths | 1 day |
|
Elvetham Road, Fleet |
Road Closure | 13/12/09 |
12 mths (original order made 07/09/09 |
1 day |
|
West Green Road, Hartley Wintney |
Road Closure | 04/01/2010 |
12 mths (original order made 04/05/09 |
9-10 wks |
|
Red Hill, Mattingley |
Road Closure | 26/11/09 |
12 mths (original order made 04/05/09 |
3 wks |
|
Laundry Lane, Heckfield |
Road Closure | 29/10/09 |
12 mths (original order made 07/09/09 |
3 wks |
|
Redfields Lane, Church Crookham |
Road Closure | 09/11/09 |
12 mths (original order made 04/05/09 |
5 days |
|
Crookham Road, Crookham Village |
Road Closure | 12/10/09 |
12 mths (original order made 04/05/09 |
3 wks |
|
Ancells Road, Farm Drive & Harvest Crescent, Fleet |
Road Closure | 09/09/09 | 12 mths | 7-10 days |
|
Crondall Lane/ Dippenhall St, Crondall |
Road Closure | w/c 10/08/09 |
12 mths (original order made 22/06/09) |
2 days |
|
Sandhurst Lane, Blackwater |
Road Closure | w/c 10/08/09 |
12 mths (original order made 22/06/09) |
2 days |
|
Hook Road North Warnborough |
Road Closure | 27/07/09 | 12 mths | 3 wks |
|
Holt Lane, Hook |
Road Closure |
17/06/09 (night-time only) |
12 mths (original order made 05/05/09) |
3-4 nights |